Phase 8

Railroad Relocation
& Consolidation

content-image

Construction started in September of 2015 with Ames Construction Inc.
as the Prime Contractor.

  • Major work included the installation of three electrical services with pre-ducted cabling for BNSF’s railroad equipment and track crossings, along with sign post with Type A signs for roadways.
  • Conduit and wiring installation was completed in the Levy Critical areas next to Mosquito Creek. Excavations required a 2:1 “V” ditch cut for trenches, with special compaction and testing requirements in order to meet the USACE levy requirements.